WIND tower sections which are part of a multi-million pound order for Kintyre firm CS Wind will ship out of Campbeltown for the next six weeks.
Dutch-registered cargo ship Arctic Rock loaded 15 sections, from a total of 99 sections, last week bound for Inverness.
From the Highland port they will be shipped by road 15.5 miles to the Dun Maglass estate at South Drumnadrochit where they will be assembled into a 33-turbine wind farm with a capacity of 94.05 mega watts.