Locomotives of any kind are rare on the Stourbridge Town branch, but heavy Type 5s are especially unusual. On March 11, Colas Railfreight No. 56090 powers a Network Rail autoballaster set at the Town end of the 0.8-mile branch.
STEPHEN BURDETT
ALMOST a mile of track was replaced on the Stourbridge Junction-Stourbridge Town branch during a seven-day blockade between March 6 and 13. The project took just eight weeks from planning to completion, a process that would normally take 18 months. The steeply-graded Stourbridge Town line is just 0.8 miles (1,287m) long.