THE overhaul of James Evans’ ex-Dinorwic Hunslet 0-4-0ST Velinheli took a major step forward on November 20, when the loco was partially dismantled and the boiler lifted. Velinheli was withdrawn in 2017 in need of a new boiler, which is being constructed at Ffestiniog Railway’s Boston Lodge works.
Hitherto the ‘Quarry Hunslet’ had been left intact, but the stage has been reached where parts of the old boiler need to be removed in order to check correct fitting in the new unit.
A fire was lit in the boiler of Richmond Light Railway’s ex- Penrhyn Hunslet 0-4-0ST Elin for the first time in over 20 years on November 18. Steam was slowly raised to 100psi in the out of frames test.