LMS ‘Jinty’ 0-6-0T No. 16440 takes shape at Swanwick Junction on July 14.
CRAIG BUXTON/
MRB
THE overhaul of LMS ‘Jinty’ 0-6-0T No. 16440 (47357) continues to make steady progress at the Midland Railway-Butterley. It is hoped a steam test can be carried out by September.
All of the boiler cladding is now fitted and the majority clamped up, with just a few finishing off areas to tackle. The boiler backhead fittings are now all fitted into place.
With the new lower section welded in place, the bunker has been lifted back onto the frames and bolted down.