Crossings consultation
NETWORK Rail has opened a consultation on proposed safety improvements at three level crossings north of Oxford where footbridges will be installed. With plans for an increase in passenger and freight workings, Network Rail plans to build a ramped footbridge and cycleway at Sandy Lane, a stepped footbridge at Yarnton Green Lane, and a new footbridge with lifts and a bridleway at Tackley. The consultation closes on July 17.
New community rail scheme for Scotland
AFTER more than three years of preparatory work, an application to the Scottish Government to have the Caithness and Sutherland section of the Far North Line (FNL) designated as the 9th Community Rail Partnership (CRP) route in Scotland has been successful. The FNL CRP aims to develop and deliver community projects, events and activities, create economic opportunities, promote the use of rail as well as moving people away from the tourism hot spots.