AS PART of a process to protect the Hereford to Abergavenny line from future washouts –a result of extreme weather conditions – Network Rail engineers have installed half-a-mile of rock armour and refurbished culverts. It is the same concept that has proved a huge success on a flood-prone stretch of the Conwy Valley line.
The £4m project began in May 2021 and in that time, 10 trains have brought more than 8000 tonnes of rock to site, locally sourced from Machen Quarry, near Newport at the southern end of the Welsh Marches route. A first phase will be completed in November with a second phase beginning in the spring.
Lisez l'article complet et bien d'autres dans ce numéro de
Railway Magazine
Options d'achat ci-dessous
Si le problème vous appartient,
Connexion pour lire l'article complet maintenant.
Numéro unique numérique
1450 - January 2022
 
Ce numéro et d'autres anciens numéros ne sont pas inclus dans une nouvelle version de l'article
abonnement. Les abonnements comprennent le dernier numéro régulier et les nouveaux numéros publiés pendant votre abonnement. Railway Magazine
Abonnement numérique annuel
€40,99
facturé annuellement
Abonnement numérique de 6 mois
€21,99
facturé deux fois par an
Abonnement numérique mensuel
€4,99
facturé mensuellement