Delay hits new ferry terminal

Brodick’s new £30 million ferry terminal will not open in August as planned, it emerged this week. Instead it is likely to be October at the earliest before passengers will get to use the new pier facilities.

This is due to a delay in the passenger access system (PAS) currently being built in Spain. The delay is all the more frustrating as the main site contractors, George Leslie Ltd, will complete the redevelopment of the ferry terminal and pier in August, on time and on budget.

READ MORE
Purchase options below
Find the complete article and many more in this issue of Arran Banner - 15th July 2017
If you own the issue, Login to read the full article now.
Single Issue - 15th July 2017
$0.99
Or 99 points
Annual Digital Subscription
SAVE
42%
$29.99
Or 2999 points
6 Month Digital Subscription
SAVE
42%
$14.99
Or 1499 points

View Issues

About Arran Banner

Local news, leisure and sport. FREE 32 page Year of History, Heritage and Archaeology supplement.