Opponents of a proposed extension to the St Molios Fish Farm in Lamlash have received notification from the Scottish Environmental Agency (SEPA) that it proposes to approve and grant a licence for the application.
The salmon farm in Lamlash Bay which has applied to SEPA for additional fish holding capacity.
01_B42sepa02
The determination of the final decision allows objectors 21 days to notify Scottish ministers in writing of their objections. The application, if approved, will allow an increase in the maximum weight of the fish held in the fish farm as well as an increase in the limitations on the use and discharge of medicines and chemicals from the farm.