AN INTENSIVE 23-day period of engineering works in and around Clacton-on-Sea saw Network Rail complete its area resignalling programme on March 14, reports Richard Horner.
The £37 million scheme included laying 500m of new track, installing 12 modern LED signals, two separate power systems, 12 new points and point motors, 13 overhead line equipment structures and more than 6000m of new cables.