PROJECT MANAGEMENT
What type of contract should I opt for?
I am finding the array of different options offered by the Joint Contracts Tribunal (JCT) very confusing. Our architect has told us that having paper copies of contracts is not advisable. We plan to appoint a builder for the main structural shell, with the possibility of procuring additional work in the future. The management building (MB) contract looks the best fit for those in my position but it is only available digitally – via a subscription and at a high cost. Are the minor works (MW) or intermediate (IC) contracts perfectly adequate?