HASSARD STACPOOLE
Work continues on the rebuilding of the Foynes line, with preparations being made to begin track laying. A new compound has been established by MP 24 at Glenbane West for contractors who are expected to start tracklaying from there towards Limerick by the end of April. In advance of tracklaying, electrical and signalling ducting has been installed on a substantial section between the compound and Adare, significant stretches of the track bed receiving an initial layer of ballast in advance of tracklaying. On February 13, looking towards Limerick, work was ongoing to establish the new compound.