The first course of ICF is always critical. In our case, the beam and block floor meant the leaf of the Nudura needed to be trimmed
When I signed offlast month, we were about to get started on the main walls and hoping to reach weathertight in time for this issue. Well, we’ve not quite made it… which just goes to show delays can happen on any project. As it turns out, this has been the most challenging phase of the Education House build so far – which is saying something given that we’ve already finished the basement shell. The good news is we’re getting re-schooled on the kind of challenges that can come up on a self build scheme and how to navigate them – so there’s plenty of learning points to share!