RECENT statistics from the Office of Rail and Road (ORR) highlight how HS2 construction traffic is helping rail freight operators bounce back from the Covid-19 pandemic.
April 1 saw the 100th train of aggregates unloaded at HS2’s main construction compound at Calvert, Buckinghamshire – the equivalent of 7,500 HGVs. DB Cargo UK and Hanson have now delivered well over 150,000 tonnes of aggregate to Calvert for the main Phase 1 works contractor EKFB.
The temporary 26,000 square metre railhead is located next to the point where HS2 crosses the route of East West Rail, and will be the main construction and logistics hub for the 80km central section of Phase 1.
HS2 Ltd will build three bridges and 3km of earthworks along the southern edge of the Calvert site on behalf of EWR.