AS WORK to reinstate the Levenmouth Rail Link from between Thornton Junction and Cameron Bridge ramps up, Network Rail is installing around 11 miles of fencing along the five-mile route as well as at some work compounds.
The fencing is to separate the public from the plant and machinery undertaking the work. Previously, work has seen the clearance of vegetation and the removal of redundant and life-expired railway equipment from the former line. Invasive plant species have been treated, structures inspected and trial holes have been drilled along the full length of the route to check ground conditions and test for contamination.