THREE major capital projects funded by Comhairle nan Eilean Siar on Barra and Vatersay are making significant progress as shown in recent aerial photographs by photographer John MacDougall.
The major harbour development at Ardveenish is nearing completion.
A £1.6m major development at Ardveenish harbour is finally nearing completion and is expected to be opened in July. The project was awarded £1.2m from the Comhairle’s Capital Programme 2008-2013 and received £283k from the Coastal Communities Fund (CCF) along with £125k from Highlands and Islands Enterprise (HIE).