Work to resurface the A85 through Lochawe has started. The improvements, costing £280,000, will be split into two phases.
Phase one began on Monday October 1 and is expected to take five days to complete. This phase will be carried out between 7am and 7pm each day.
The road will remain open, but temporary traff c lights and a traff c convoy will be in place to ensure the safety of road workers and motorists. The second phase of resurfacing starts on Sunday October 14 and is expected to take five nights, finishing on the morning of Friday October 19.