PROJ ECT PLANNER
This example build schedule will help you account for the key milestones on your self build journey
WEEKS 1-2 Preliminaries
Notify building control (BC) of commencement at least 48 hours before work begins
Create suitable site access
Clear plot and strip topsoil (possibly for later reuse)
Set up land in accordance with the site plan
Arrange temporary services (electricity & water)
Form secure storage on site
Install site office, portaloo and temporary fencing
Mark out the foundations (may require a surveyor)
KEY
BOTH SYSTEMS
MASONRY ONLY
TIMBER FRAME ONLY
WEEKS 2-3 Foundations & oversite
Dig foundation trenches and wait for BC inspection
Fit foundation reinforcement and pour concrete (inspection may be required)